With the warmer weather Wednesday, our volunteers were able to get outside for a few hours to continue work on the siding. Two sides of the home are now fully sided!

Work on the home continues this weekend, with build days Friday, Saturday and Sunday. The build site is open from 8:30am to 4:30pm, with both morning and afternoon build shifts available. All skill levels are welcome- we enjoy helping people learn new skills.  To find out more, stop by the build site (7415 Railway Avenue).

Our tasks for this weekend include:
  • complete hanging drywall on the main floor
  • complete mudding on the 2nd floor
  • start taping/mudding on the main floor
  • siding (if weather permits)

Our goal is to be ready for paint on the second floor by the end of the weekend!